Case Study:

Westende Junior School, Wokingham,

Westende Junior School, Wokingham,

Scope of works and general description of work undertaken:

Agripower were delighted when they were recently awarded this tender through Wokingham District Council. The objective was to build a fenced multi use games area which was suitable for a Junior Schools sporting curriculum.

The project included: Clearing vegetation, installation of drainage, concrete edgings, colour coated acrylic surface, twin bar fencing.

The surface chosen was painted, water based, acrylic.

Key sub-contractors employed to undertake works Address: All works were done in-house

The project was delivered within the program budget and ahead of time. Agripowers competent team of installers completed the project during the summer term, the school was still busy with holiday clubs so communication was paramount


Project details:

Value: £90,000

Duration: 7 weeks